Start from the first production date after the summer shutdown and work backwards. Give each stage a site owner and an explicit handoff. The dismantling team needs a release from the old site while the installer needs confirmed utilities and access at the new one.
Protect the sequence before fixing dates
Record what can happen before the shutdown and which tasks must wait. Keep supplier availability, transport clearance and the site acceptance window visible. Together with the project team, identify any contingency period before customer orders depend on the new line.
| Activity | Prerequisite | Illustrative duration |
|---|---|---|
| Release and label equipment | Last production and signed scope | 1 day |
| Dismantle and load | Lift plan and transport readiness | 2 days |
| Install and connect | Destination ready and modules identified | 3 days |
| Trial and production release | Samples, personnel and approved criteria | 2 days |
If these example stages run in sequence, the sum is eight days. Add the travel time and any buffer separately, using confirmed dates.
Use the inspection and relocation checklist for the handover